June 3, 2025
The milling and paving activities on the 95/395 Express Lanes from near Franconia-Springfield Parkway to near Edsall Road are concluding; that segment of the Express Lanes is expected to be fully open to traffic overnight beginning the evening of Thursday, August 7, 2025.
The project will continue further south, with milling and paving activities scheduled to begin the evening of Thursday August 7, from MM 170 to MM 158 on the 95 Express Lanes:
Day |
Time |
Closure Type |
Monday-Thursday |
8 p.m. – 10 p.m. |
Two-lane closure |
|
10 p.m. – 4 a.m. |
Full closure |
Friday |
9 p.m. – 8 a.m. |
Two-lane closure |
Saturday (backup) |
8 p.m. – 8 a.m. |
Two-lane closure |
Sunday (backup) |
8 p.m. – 10 p.m. |
Two-lane closure |
|
10 p.m. – 4 a.m. |
Full closure |
Southbound traffic will be diverted to the general-purpose lanes via the flyover ramp near Backlick Road; travelers can re-enter the Express Lanes via the slip ramp near Dale Boulevard. Following reversal, northbound traffic will be diverted off the Express Lanes to the general-purpose lanes via the slip ramp near Prince William Parkway; travelers can re-enter the Express Lanes via the slip ramp north of Franconia-Springfield Parkway.