Plan Ahead: Overnight Stoppages Near American Legion Road Overpass in Stafford, VA Beginning September 26

September 22, 2022

Overnight construction on I-95 South to lift and install bridge beams for a replacement American Legion Road overpass is scheduled for September 26-28. Intermittent full traffic stops are scheduled between 11:00 p.m. and 4:00 a.m. with each stop lasting up to 30 minutes at a time. Overnight construction on I-95 North to lift and install bridge beams for a replacement American Legion Road overpass is scheduled for October 3-5. Intermittent full traffic stops are scheduled between 11:00 p.m. and 4:00 a.m. with each stop lasting up to 30 minutes at a time. Travelers are advised to plan ahead and reroute their travel to avoid delays from the intermittent stoppages.  

*Tentatively scheduled for September 26- September 28 and October 3-October 5. 

Visit www.expresslanes.com/news-and-alerts for detour and up-to-date road closure information.

About the 95 Express Lanes Fredericksburg Extension Project

To make traveling through the I-95 corridor in Stafford County easier and faster, the Fredericksburg Extension (Fred Ex) will pick up where the 95 Express Lanes currently end and will extend 10 miles south near Fredericksburg, VA. The lengthened lanes will connect with the 395 Express Lanes to create a connected corridor spanning nearly 50 miles from the Fredericksburg area to the D.C. line.

This project will also offer new access points to the existing 95 Express Lanes, create new ramps that provide direct access to Quantico and Courthouse Road, and add seven new bridges. When the Fred Ex project is completed, it will connect with the 395 Express Lanes, offering drivers an uninterrupted Express Lanes corridor between the Potomac River and near the Rappahannock River.
 
More information on the Fred Ex project and 95 Express Lanes is available at www.expresslanes.com.